 Topbondrecently completed the refurbishment of four reinforced concrete footbridges during some changeable spring time weather.

 All four bridges, which were located at a busy road interchange were identical and the work involved traffic management, the removal of the existing failed surfacing and expansion joints, preparation of the deck, including concrete repairs and the application of a combined waterproofing and anti skid wearing course and the refurbishment of the drainage system.

 Topbond worked on one bridge at a time and were able to complete all works to a bridge in a 1 week cycle meaning disruption to the bridge users was minimised.